Civil Infrastructure Works for the week ending 9 December 2022

  • Continue Tolleys Gully Construction
  • Continue dig outs MR73 south
  • Complete dig out Rock Abbey Road
  • Commence dig outs Barraba Road
  • Complete grading Baldersleigh Road
  • Commence grading Barraba Road
  • Commence slashing rural and regional roads
  • Continue tar patching rural and regional roads
  • Continue mowing in Uralla and Bundarra

Planned works next week, commencing 12 December 2022

  • Continue Tolleys Gully Construction
  • Continue dig outs MR73
  • Continue dig outs Barraba Road
  • Complete grading Barraba Road
  • Continue slashing rural and regional roads
  • Continue tar patching rural and regional roads
  • Continue mowing in Uralla and Bundarra

 

 

 

 

 

 

 