Council Works Report 8 September 2023
Civil Infrastructure works undertaken week ending 8 September 2023:
- Complete grading Retreat Road
- Complete grading Georges Creek Road
- Continue grading Clerks Creek Road
- Complete grading Green Gully Road
- Complete grading Water Works Road
- Complete grading Race Course Road
- Continue works The Glen Project
- Commence grading Rifle Range Road
- Continue tar patching regional and rural roads
- Continue footpaths, parks and cemeteries Uralla and Bundarra
Planned works for week commencing 11 September 2023
- Stabilise Ferndale Hill Rehab
- Complete grading Clerks Creek Road
- Commence grading Barraba Road
- Commence grading Castle Drive
- Commence grading Leece Road
- Commence grading Quartz Gully Road
- Commence grading Balala Road
- Continue works The Glen Project
- Continue footpaths, parks and cemeteries maintenance Uralla and Bundarra