Council Works Report 5 November 2021

Civil Infrastructure Works for the week ending 5 November 2021

  • Complete clearing and continue earth works on Tolleys Gully construction (see photo)
  • Complete storm water drainage in John Street
  • Complete grading Barraba Road (see photo)
  • Complete grading Old Wollun Road
  • Complete regrading Clerks Creek Road
  • Continue grading Carlon Menzies Road
  • Commence heavy patches on MR73 South (using contractor Stablecorp)
  • Continue tar patching on rural and regional roads
  • Continue mowing in Uralla and Bundarra
  • Complete backfilling Oliver Street footpath (see photo)

Works scheduled next week, commencing 8 November 2021

  • Continue earth works on Tolleys Gully Construction
  • Commence pipe extensions on Bergen Road construction
  • Commence installing 2 new sets of pipes on Karingal Road
  • Complete grading Carlon Menzies Road
  • Complete grading Clerks Creek Road
  • Commence grading Gowans Road
  • Continue tar patching on rural and regional roads
  • Continue mowing in Uralla and Bundarra
  • Complete heavy patches on MR73 South (using contractor Stablecorp)
  • Commence heavy patches on MR73 Central (using contractor Stablecorp) 