Council Works Report 5 May 2023

Civil Infrastructure works undertaken week ending 5 May 2023:

  • Complete batters and base coarse on Mr73 North from the lone Pine Bridge to the Sporting Club ready for final trim and sealing in Bundarra
  • Complete carting gravel onto Gostwyck Road Rehabilitation
  • Complete grading Retreat Road
  • Commence grading Bendemeer Road
  • Commence grading and graveling Barraba Road where it was damaged by floods
  • Complete patching Yarrowyck Crossing Causeway damaged by floods (temporarily)
  • Continue tar patching on regional and rural roads
  • Commence mowing recreation areas
  • Continue sign maintenance on rural roads
  • Complete slashing Rocky River Road
  • Continue mowing in Uralla and Bundarra
  • Continue foot maintenance in Uralla

Planned works for week commencing 8 May 2023:

  • Complete final trim and sealing on Mr73 North from Lone Pine Bridge to the Sporting Club in Bundarra
  • Commence reworking gravel on Gostwyck Road Rehabilitation ready for Stabilising
  • Complete graveling flood damage on Barraba Road
  • Continue grading Barraba Road
  • Continue grading Bendemeer Road
  • Continue tar patching on rural and regional roads
  • Complete grading Hillview Road using contractor Wally Schalk
  • Commence renewing causeway on Danehurst Road
  • Continue mowing in Uralla and Bundarra
  • Continue footpath maintenance in Uralla
  • Complete marking lines for small school athletic carnivals

 

 

 

 

 