Civil Infrastructure Works for the week ending 4 June 2021

  • Continued digging out wet spots on Hawthorne Drive Construction (see photo below).
  • Continued grading Hillview Road.
  • Grading Ingledale Road.
  • Commenced grading Ross Road.
  • Grading Lawson’s Road.
  • Commenced grading Primrose Road.
  • Commenced BBQ shade structures at the Bundarra Multipurpose Courts.
  • Continued tar patching on rural roads.
  • Continued tree maintenance in Uralla and Bundarra.
  • Ceased storm drainage until the pipes are delivered.
  • Continued drainage on rural roads.

Hawthorne-Drive-Construction.jpg

     

    Works scheduled next week, commencing 7 June 2021

    Rural-Road-Maintenence.jpg

    • Complete digging wet spots out and start bringing in base course on Hawthorn Drive Construction.
    • Complete backfilling box culverts on Spring Gully Road.
    • Complete grading Ross Road.
    • Recommence grading Spring Gully Road.
    • Complete grading Primrose Road.
    • Complete grading Pansyfield Road.
    • Complete grading Hillview Road.
    • Complete grading Martin Lane.
    • Complete grading Haynes Lane.
    • Complete grading Dorlie Lane.
    • Complete grading Bakers Lane.
    • Commence grading Glenroy Road.
    • Commence shared footpath in Plane Avenue.
    • Continue tar patching on rural and regional roads.
    • Complete shade structures, BBQs, tables and seats at the Bundarra Multipurpose Courts.
    • Continue drainage on rural roads.
    • Continue tree maintenance in Uralla and Bundarra.