Council Works Report 4 February 2022

Civil Infrastructure Works for the week ending 4 February 2022

  • Suspended Tolleys Gully Construction due to the wet weather
  • Completed graveling Martin Lane and Hayes Lane
  • Suspended maintenance grading due to the rain
  • Continued tar patching on Kingstown Road
  • Completed slashing Invergowrie area/MR124 Bundarra Road, commenced MR73 Central
  • Continued mowing and weed spraying in Uralla and Bundarra
  • Continued drainage on rural roads
  • Commenced cleaning sediment traps in Uralla
  • Continued cleaning up limbs in town after the storm

Rural-Road-Maintenence.jpg

Works scheduled next week, commencing 7 February 2022

  • Recommence Tolleys Gully Construction of approaches (see photo)
  • Recommence grading Baldersleigh Road
  • Grade Martin Lane, Hayes Lane, and Glenroy Road where recently gravelled
  • Continue tar patching on Kingstown Road and regional roads (see photo)
  • Continue slashing on regional roads and rural roads
  • Continue drainage on rural roads
  • Continue mowing and weed spraying in Uralla and Bundarra