Council Works Report 30 June 2023

Civil Infrastructure works undertaken week ending 30 June 2023:

  • Complete grading Linfield Road
  • Complete grading Gostwyck Road
  • Commence grading Carlon Menzies Road
  • Complete grading Mt Drummond Road
  • Commence grading and gravelling Stoney Batter Road
  • Continue grading and gravelling Gap Road
  • Continue tar patching regional and rural roads
  • Complete pipe replacement Balala Road
  • Continue drainage works rural roads
  • Complete slashing Kentucky areas
  • Complete slashing MR 73
  • Commence slashing Kingstown area
  • Continue clean up kerb and gutters Uralla and Bundarra
  • Continue footpath and parks maintenance Uralla and Bundarra

 

 

Planned works for week commencing 3 July 2023

  • Complete grading Linfield Road
  • Complete grading Gostwyck Road
  • Commence grading Carlon Menzies Road
  • Complete grading Mt Drummond Road
  • Commence grading and gravelling Stoney Batter Road
  • Continue grading and gravelling Gap Road
  • Continue tar patching regional and rural roads
  • Complete pipe replacement Balala Road
  • Continue drainage works rural roads
  • Complete slashing Kentucky areas
  • Complete slashing MR 73
  • Commence slashing Kingstown area
  • Continue clean up kerb and gutters Uralla and Bundarra
  • Continue footpath and parks maintenance Uralla and Bundarra

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Rural-Road-Maintenence.jpg