Council Works Report 3 May 2024
Civil Infrastructure works undertaken week ending 3 May 2024:
- Complete granite overlay Scrubby Gully
- Continue pipe and batter works Scrubby Gully
- Complete grading Blue Mountain Road
- Continue grading Hillview Road
- Renew pipes Baldersleigh Road
- Commence road repairs Bundarra Streets
- Continue tar patching regional and rural roads
- Continue signs maintenance
- Continue maintenance footpaths parks and cemeteries
- Commence line marking sports fields
- Commence water meter readings
Planned works for week commencing 6 May 2024
- Stabilize Scrubby Gully
- Continue pipe and batter works Scrubby Gully
- Continue grading Hillview Road
- Commence grading Bakers Creek Road
- Continue tar patching regional and rural roads
- Continue maintenance footpaths parks and cemeteries
- Continue line marking sports fields
- Continue reading water meters