Council Works Report 28 May 2021

Civil Infrastructure Works for the week ending 28 May 2021

  • Guard rail on MR73 South Tarana Construction (see photo)
  • Continued working wet spots on Hawthorne Drive Construction (see photos)
  • Continued grading Hillview Road
  • Grading Ferris Lane
  • Grading Mundays Lane
  • Grading Yellow Box Lane
  • Grading Lagoon Road
  • Commenced grading Lawson Road
  • Commence grading Spring Gully Road
  • Continued wing walls and back filling box culverts on Spring Gully Road (see photo)
  • Continued tar patching MR73 Central and Rural Roads
  • Commenced storm water pipes in John Street
  • Marking running tracks for small school  sports carnivals
  • Continued mowing and tree maintenance in Uralla and Bundarra
  • Water meter readings in Uralla
  • Commenced heavy patching on Thunderbolts Way (south of Uralla), and Kingstown Road 6km from Uralla (by contractor)

 

Works scheduled next week, commencing 31 May 2021

Rural-Road-Maintenence.jpg

  • Complete digging wet spots out and carting base course in on Hawthorne Drive Construction
  • Complete pouring wing walls and back filling box culverts on Spring Gully Road
  • Commence grading Ingledale Road
  • Complete grading Hillview Road
  • Complete grading Lawson Road
  • Commence grading Pansyfield Road
  • Complete storm drainage pipes in John Street
  • Continue tar patching on MR73 North
  • Complete building shelters and barbecues in Bundarra
  • Commence shared path in Plane Avenue