Council Works Report 28 April 2023
Civil Infrastructure works undertaken week ending 21 April 2023:
- Complete carting base course on Mr73 North ready for final trim
- Complete graveling Hill Top Lane in Bundarra
- Complete graveling Burnet Street in Bundarra
- Complete drainage on Gostwyck Road Rehabilitation
- Commence graveling on Gostwyck Road Rehabilitation
- Commence grading Retreat Road
- Complete signs on Hawthorn Drive Construction
- Commence tar patching on Mr73 Central
- Continue mowing in Uralla and Bundarra
- Continue footpath maintenance in Uralla
- Complete marking sporting fields for small schools athletic carnival
Planned works for week commencing 1 May 2023:
- Complete final trim on Mr73 North ready for sealing and complete batters
- Continue graveling Gostwyck Road rehabilitation
- Complete grading Retreat Road
- Commence renewing causeway on Danehurst Road
- Continue tar patching on Mr73 Central
- Continue mowing in Uralla and Bundarra
- Continue foot path maintenance in Uralla
![Rural-Road-Maintenence.jpg](/files/assets/public/v/1/council-services/works-updates/2019/rural-road-maintenence.jpg?w=1152&h=864)