Council Works Report 28 April 2023

Civil Infrastructure works undertaken week ending 21 April 2023:

  • Complete carting base course on Mr73 North ready for final trim
  • Complete graveling Hill Top Lane in Bundarra
  • Complete graveling Burnet Street in Bundarra
  • Complete drainage on Gostwyck Road Rehabilitation
  • Commence graveling on Gostwyck Road Rehabilitation
  • Commence grading Retreat Road
  • Complete signs on Hawthorn Drive Construction
  • Commence tar patching on Mr73 Central
  • Continue mowing in Uralla and Bundarra
  • Continue footpath maintenance in Uralla
  • Complete marking sporting fields for small schools athletic carnival

 

Planned works for week commencing 1 May 2023:

  • Complete final trim on Mr73 North ready for sealing and complete batters
  • Continue graveling Gostwyck Road rehabilitation
  • Complete grading Retreat Road
  • Commence renewing causeway on Danehurst Road
  • Continue tar patching on Mr73 Central
  • Continue mowing in Uralla and Bundarra
  • Continue foot path maintenance in Uralla

 

 

 