Council Works Report 26 May 2023
Civil Infrastructure works undertaken week ending 26 May 2023:
- Complete drainage, pipe extensions, and stabilising on Gostwyck Road Rehabilitation ready for sealing
- Complete grading Barraba Road
- Commence grading and gravelling Mt Drummond Road
- Complete grading Bendemeer Road
- Commence Grading Box Forrest Rd
- Complete Danehurst Road Causeway
- Commence Balala Road Causeway
- Continue tar patching MR73 south
- Complete tar patching Invergowrie Area
- Complete slashing Torryburn Road
- Continue removal fallen trees at sporting complex
- Continue street tree pruning
- Continue mowing Uralla and Bundarra
- Continue drainage rural roads
- Continue sign maintenance rural roads
- Commence shared footpath Plane Avenue
Planned works for week commencing 29 May 2023:
- Complete sealing Gostwyck Road rehab
- Complete grading Box Forrest Road
- Commence grading and gravelling Yarrawyck Crossing Road
- Continue grading and Gravelling Mt Drummond Road
- Continue causeway Balala Road
- Continue tar patching MR73 south
- Commence tar patching Mr124
- Continue drainage rural roads
- Continue sign maintenance rural roads
- Continue street tree pruning Uralla
- Commence clean up kerb and gutters