Council Works Report 26 August 2022

Civil Infrastructure Works for the week ending 26 August 2022

  • Complete drainage on Hawthorne Drive construction (cease work until it dries out)
  • Continue gravel resheeting and grading Dog Trap Road
  • Complete grading and graveling Hallway Lane
  • Complete grading and spot graveling Saumarez War Service Road
  • Complete grading Thomas Lagoon Road
  • Complete grading Jacksons Road
  • Complete grading Mount Butler Lane
  • Complete grading Amaroo Road
  • Complete grading Wallinga Road
  • Complete grading Tabulam Road
  • Continue grading Bakers Creek Road
  • Commence drainage on Primrose Hill Road
  • Continue tar patching Invergowrie/Dumaresq areas
  • Continue tar patching regional roads
  • Commence refurnishing chairs in the main street
  • Continue footpath and kerb and gutter maintenance
  • Continue whipper snipping in Uralla and Bundarra

Barbatos-Corner.jpg

 

Works scheduled next week, commencing 29 August 2022

  • Complete grading and graveling Dog Trap Road
  • Complete grading Wallaby Rocks Lane
  • Commence grading Devoncourt Road
  • Complete grading Bakers Creek Road
  • Commence grading Georges Creek Road
  • Complete grading Adina Road
  • Complete grading Kooda Road
  • Complete grading Lantana Road
  • Complete grading Kareela Road
  • Complete grading Malapatinti Road
  • Complete drainage on Pansyfield Road and Primrose Hill Road
  • Win gravel to spot gravel Pansyfield and Primrose Hill Roads
  • Fix wash outs on Danehurst and Warrabah Roads
  • Continue tar patching in Invergowrie and Dumaresq Roads
  • Continue tar patching on regional roads
  • Commence kerb and gutter in Roman Street
  • Commence mowing and weed spraying in Uralla and Bundarra
  • Continue refurnishing seats in the main street
  • Continue foot path and kerb and gutter maintenance in Uralla

 