Civil Infrastructure works undertaken week ending 25 August 2023:
- Granite overlay Ferndale Hill reconstruction
- Drainage and batter works Ferndale Hill
- Completed grading Westvale Road
- Commenced grading Warrembah Road
- Gravel resheeting Warrembah Road
- Recommenced grading Old Kingstown Road
- Signs maintenance Thunderbolts Way South
- Continue footpaths, parks and cemetery maintenance Uralla and Bundarra
- Continued tar patching Thunderbolt’s Way North, edges and potholes
Planned works for week commencing 28 August 2023
- Continue granite overlay Ferndale Hill reconstruction
- Continue drainage and batter works Ferndale Hill
- Grading Waterworks Road
- Grading Green Gully Road
- Grading Racecourse Road
- Grading Lookout Road
- Line marking newly sealed Roads (contractor)
- Commence tar patching Bundarra Road (to Armidale)
- Assist with The Glen Precinct Project
- Tree pruning and removal at The Glen
- Continue footpaths, parks and cemetery maintenance Uralla and Bundarra