Council Works Report 24 February 2023
Civil Infrastructure Works for the week ending 24 February 2023
- Continue base on Hawthorne Drive
- Continue gravelling and grading Bindawalla Road
- Continue gravelling and grading Lindon Road
- Continue footpath bridge upgrade Bundarra
- Continue tar patching on regional and rural roads
- Continue mowing and vegetation control Uralla and Bundarra
Planned works next week, commencing 27 February 2023
- Continue base Hawthorne Drive
- Complete gravelling grading Bindawalla Road
- Commence drainage and grading Barraba Road
- Continue grading Lindon Road
- Continue tar patching regional and rural Roads
- Continue mowing and vegetation control Uralla Bundarra
- Commence roadside slashing regional and rural roads