Council Works Report 23 August 2024
Civil Infrastructure works undertaken week ending 23 August 2024
- Complete grading Warrabah and Bendemeer Roads
- Complete pipe and drainage works Warrabah and Bendemeer Roads
- Complete pipe replacement Gap Road
- Complete grading Yarrowyck Crossing and Reids Road
- Complete grading Barraba Road
- Commence drainage works around Bundarra
- Continue tar patching MR73
- Continue maintenance footpaths parks and cemeteries
- Commence preparing flower beds Alma Park
Planned works for week commencing 26 August 2024
- Re-commence works Kingstown Road rehabilitation
- Grade Box Forrest Road
- Grade Rowbottoms Road
- Grade Jenkyn’s Lane
- Continue pipe and drainage works Bundarra
- Commence pipe and drainage works Uralla
- Continue tar patching regional and rural roads
- Continue maintenance footpaths parks and cemeteries