Council Works Report 22 October 2021

Civil Infrastructure Works for the week ending 22 October 2021

  • Completed patching the worst of the interim patches on Northeys Road and MR73 south (see photo)
  • Completed sealing interim patches on Kliendienst Road
  • Commenced sealing interim patches on Northeys Road and Arding Road
  • Continued clearing on Hawthorne Drive Construction Stage 2
  • Completed grading Blue Mountain Road
  • Recommenced grading on Hillview Road
  • Completed grading Salisbury Plains Road
  • Recommenced grading Gap Road
  • Completed grading Athol Road
  • Commenced grading Karingal Road
  • Continued footpath in Oliver Street, Bundarra
  • Continued tar patching on MR73 central
  • Continued mowing in Uralla and Bundarra
  • Bitumen Crews working flexi days and Saturdays to try and catch up with all the potholes and major failures on rural and regional roads
Patching.jpg

 

Works scheduled next week, commencing 25 October 2021

  • Recommence Tolleys Gully Construction approaches and drainage
  • Complete clearing on Hawthorne Drive Construction Stage 2
  • Complete sealing interim patches on Arding Road and Northeys Road
  • Continue tar patching on regional roads
  • Complete grading Hillview Road
  • Complete grading Gap Road
  • Commence grading Traceys Road
  • Complete grading Karingal Road
  • Complete footpath in Oliver Street, Bundarra
  • Continue mowing in Uralla and Bundarra 