Council Works Report 18 August 2023
Civil Infrastructure works undertaken week ending 18 August 2023:
- Completed grading Bakers Lane
- Completed grading Brechts Road
- Completed grading Plug Street
- Completed grading Mabbots Road
- Completed grading Wesvale Road
- Commence grading Warrembah Road
- Completed grading Karingal Road
- Recommence grading Old Kingstown Road
- Completed pavement seal Two Mile Rehabilitation
- Complete guide posting and spot marking for line marking Two Mile, when scheduled
- Continue tar patching Thunderbolt’s Way North
- Commenced drainage and batter works at Ferndale Hill Rehabilitation
- Cleaned up old storm damage trees around regional roads
- Continue footpaths, parks and cemetery maintenance Uralla and Bundarra
Planned works for week commencing 21 August 2023
- Start carting granite to Ferndale Hill rehabilitation
- Continue grading Warrembah Road
- Continue grading Old Kingstown Road
- Commence grading Waterworks Road
- Commence grading Green Gully Road
- Commence grading Racecourse Road
- Commence grading Lookout Road
- Commence grading Rifle Range Road
- Assist with The Glenn Precinct Project
- Continue clearing pipes on Bendemeer Road
- Continue maintenance footpaths, parks and cemeteries Uralla and Bundarra