Civil Infrastructure works undertaken week ending 18 August 2023:

  • Completed grading Bakers Lane
  • Completed grading Brechts Road
  • Completed grading Plug Street
  • Completed grading Mabbots Road
  • Completed grading Wesvale Road
  • Commence grading Warrembah Road
  • Completed grading Karingal Road
  • Recommence grading Old Kingstown Road
  • Completed pavement seal Two Mile Rehabilitation
  • Complete guide posting and spot marking for line marking Two Mile, when scheduled
  • Continue tar patching Thunderbolt’s Way North
  • Commenced drainage and batter works at Ferndale Hill Rehabilitation
  • Cleaned up old storm damage trees around regional roads
  • Continue footpaths, parks and cemetery maintenance Uralla and Bundarra

 

Planned works for week commencing 21 August 2023

  • Start carting granite to Ferndale Hill rehabilitation
  • Continue grading Warrembah Road
  • Continue grading Old Kingstown Road
  • Commence grading Waterworks Road
  • Commence grading Green Gully Road
  • Commence grading Racecourse Road
  • Commence grading Lookout Road
  • Commence grading Rifle Range Road
  • Assist with The Glenn Precinct Project
  • Continue clearing pipes on Bendemeer Road
  • Continue maintenance footpaths, parks and cemeteries Uralla and Bundarra

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 