Council Works Report 17 September 2021

Civil Infrastructure Works for the week ending 17 September 2021

  • Sealing works commenced by Green Light Contractors on Big Ridge Road segments 1 and 3 (see photos)
  • Completed grading Mt Butler Lane
  • Completed grading Rosehill Road
  • Completed grading Saumarez War Service Road
  • Completed grading Dwyers Range Road
  • Completed grading Mihi Road
  • Completed grading Linfield Road
  • Completed grading Evertonvale Road
  • Completed grading Kalinowski Lane
  • Completed grading Rifle Range Road
  • Completed street furniture refurbishment
  • Completed drainage works Hawthorne Drive construction Stage 1
  • Continued sign maintenance in Uralla and rural roads
  • Continued with Tolleys Gully Bridge abutments – road design finalised and pegged out
  • Continued tar patching regional and rural roads
  • Removed privet from Uralla Creek
  • Completed upgrade to Bendemeer Street Bundarra footpath (see photo) 

 

Works scheduled next week, commencing 20 September 2021

  • Continue tar patching on rural and regional roads
  • Continue drainage in Uralla and rural roads
  • Continue multipurpose sports courts Bundarra
  • Continue Tolleys Gully Bridge abutments
  • Commence grading Gostwyck Road
  • Commence grading Lindon Road and Athol Road
  • Commence mowing in Uralla town area 