Council Works Report 15 July 2022

Civil Infrastructure Works for the week ending 15 July 2022

  • Continue Sub Base on Hawthorne Drive Construction
  • Complete grading Ingledale Road
  • Complete grading Spring Gully Road
  • Commence grading Barraba Road
  • Complete installing 2 set of pipes on Gwydir Park Road
  • Commence Tar Patching Arding and Dumaresq Roads
  • Drain Terrible Vale Road Heavy Patch
  • Continue cleaning gutters and footpaths in Uralla and Bundarra
  • Continue drainage on rural roads
  • Continue guide posting on rural roads
  • Continue heavy patching on Kingstown Road
  • Mark out give way lines at Barbatos Corner ready for line marking
  • Dot centre line from Barbatos Corner to Marble Hill Road (Bundarra Road)

 

Works scheduled next week, commencing 18 July 2022

  • Continue Sub Base on Hawthorne Drive Construction
  • Complete grading Barraba Road
  • Commence grading Mihi Road
  • Continue tar patching on Arding and Dumaresq Roads
  • Complete kerb and gutter repairs in Bligh Avenue
  • Commence delivering pipes to Bindawalla Road ready to install
  • Continue drainage on rural roads
  • Continue guide posting on rural roads
  • Complete heavy patching on Kingstown Road

 