Council Works Report 14 July 2023
Civil Infrastructure works undertaken week ending 14 July 2023:
- Continue grading Carlon-Menzies Road
- Complete grading Gap Road
- Complete grading Salisbury Plains Road
- Complete grading Talisker Road
- Complete grading Stoney Batter Road
- Commence gravelling and grading Hardens Road
- Commence rehabilitation work Two Mile
- Continue tar patching regional and rural Roads
- Continue pipe works Bendemeer Road
- Continue sign and guide post maintenance regional and rural Roads
- Continue footpath and parks maintenance Uralla and Bundarra
Planned works for week commencing 17 July 2023
- Continue Rehabilitation works two mile MR73 North
- Continue grading Carlon-Menzies Road
- Continue gravelling and grading Hardens Road
- Complete sealing works Roman Street
- Continue tar patching regional and rural Roads
- Continue sign maintenance regional and rural Roads
- Continue footpath and parks maintenance Uralla and Bundarra