Council Works Report 12 January 2024

Civil Infrastructure works undertaken week ending 12 January 2024:

  • Complete gravel overlay Kingstown Road
  • Complete grading Barraba Road (damaged in storm over the Christmas break)
  • Commence grading Yarrowyck Crossing Road
  • Continue grading Baldersleigh Road
  • Continue pipe work industrial area
  • Continue tar patching regional and rural roads
  • Commence water main renewal Hill Street
  • Continue maintenance footpaths parks and cemeteries

Planned works for week commencing 15 January 2024 

  • Stabilise Kingstown Road rehabilitation
  • Continue grading Baldersleigh Road
  • Continue grading Yarrowyck Crossing Road
  • Commence grading Reids Road
  • Complete water main renewal Hill Street
  • Complete works industrial area
  • Recommence slashing regional and rural roads
  • Continue tar patching regional and rural roads
  • Continue maintenance footpaths parks and cemeteries

 

 

 

 