Council Works Report 1 March 2024

Civil Infrastructure works undertaken week ending 1 March 2024:

  • Continue Rehabilitation Tolleys - Scrubby batter and drainage works
  • Complete grading Ameroo Road
  • Complete grading Bakers Road
  • Complete grading Budumba Road
  • Complete grading Kalinda Road
  • Commence grading Mt Buttler Lane
  • Continue grading Bendemeer Road
  • Commence grading Warrabah Road
  • Continue tar patching regional and rural roads
  • Continue slashing regional and rural roads
  • Continue maintenance footpaths parks and cemeteries

 

Planned works for week commencing 4 March 2024 

  • Continue rehabilitation Tolleys - Scrubby Batters and drainage
  • Continue grading Mt Butler Road
  • Commence grading Rosehill Road
  • Continue grading Bendemeer Road
  • Continue grading Warrabah Road
  • Continue tar patching regional and rural roads
  • Continue slashing regional and rural roads
  • Continue maintenance footpaths parks and cemeteries

 

 

 

 

 

 

 