Council Works Report 1 July 2022

Civil Infrastructure Works for the week ending 1 July 2022

  • Continue boxing out and carting gravel for sub base on Hawthorne Drive Construction
  • Continue grading Hillview Road
  • Complete grading Ross Road
  • Commence grading Spring Gully Road
  • Continue tar patching on MR73 South and MR73 Central
  • Complete Park Street school crossing except for asphalting and signage
  • Continue tree clearing in Alma Park after the storm
  • Continue mowing in Uralla and Bundarra
  • Continue gutter maintenance Uralla
  • Complete stabilising on Kliendienst Road (see photo)
  • Commence stabilising on Kingstown Road (see photo)

Works scheduled next week, commencing 4 July 2022

  • Continue carting gravel for sub base ready for stabilising on Hawthorne Drive Construction
  • Complete grading Hillview Road
  • Commence grading Mihi Road
  • Complete grading Spring Gully Road
  • Complete signage on the school crossing at Park Street
  • Commence Kerb and Gutter renewal in Bligh Avenue
  • Continue tar patching on MR73 South and MR73 Central
  • Continue mowing in Uralla and Bundarra
  • Continue gutter maintenance in Uralla
  • Continue stabilising on Kingstown Road

 