Council Works Report 1 April 2022

Civil Infrastructure Works for the week ending 1 April 2022

Wet weather impacted programmed works.

  • Ceased Hawthorne Drive construction
  • Ceased maintenance grading for 3 days
  • Recommenced grading and gravel resheeting Sanctuary Drive
  • Graded heavy patch shoves on Kingstown Road, MR73, Kentucky, Bergen and Enmore Roads
  • Continued tar patching on MR124 and Gwydir River Road
  • Swept Old Gostwyck, Hariet Gully, Corey, Bergen, Terrible Vale and Rocky River Roads
  • Continued drainage and guide post maintenance on rural roads
  • Completed tree maintenance at Fuller Park
  • Completed kerb and gutter maintenance at Alma Park
  • Completed excavation of new cell at Bundarra landfill
  • Continued whipper snipping around guard rail on bridges
  • Continued mowing in Uralla and Bundarra

bergen-road.jpg

Works scheduled next week, commencing 4 April 2022

  • Recommence Hawthorne Drive Construction pipe extensions
  • Complete grading and gravel resheeting Sanctuary Drive
  • Commence grading and gravel resheeting Rock Abbey Road
  • Commence grading Gwydir Park Road
  • Complete grading Racecourse Lagoon Road, got washed out last week
  • Continue tar patching MR124 and rural roads
  • Continue drainage on rural roads
  • Recommence slashing on rural roads
  • Mark sporting fields for athletic carnival
  • Continue mowing and weed spraying in Uralla and Bundarra

 