Council Works Report 2 February 2024

Civil Infrastructure works undertaken week ending 2 February 2024:

  • Commence Tolleys – Scrubby Gully Rehabilitation
  • Complete grading Retreat Road
  • Complete grading Goldsworth Road
  • Complete grading Maitland Point Road
  • Complete grading Rowbottoms Road
  • Commence grading Primrose Hill Road
  • Complete grading Baldersleigh Road
  • Continue tar patching town area
  • Continue slashing regional and rural roads
  • Continue pipe and drainage in various areas
  • Continue maintenance footpaths parks and cemeteries

 

Planned works for week commencing 5 February 2024

  • Commence granite overlay Tolleys –Scrubby Gully
  • Complete grading Primrose Hill Road
  • Commence grading Panseyfield Road
  • Commence grading Georges Creek Road
  • Continue tar patching regional and rural roads
  • Continue slashing regional and rural roads
  • Continue maintenance and repairs pipes and drains various areas
  • Continue maintenance footpaths parks and cemeteries

 

 

 

 

 

 

 